New regional policing facility
Background
The current station on Main Street was built in the 1970s when Moncton had a much smaller-scale police force.
Fast forward to the 1990s, when the local police force was converted to a tri-community force, offered by what is now known as the Codiac Regional RCMP (serving Moncton, Dieppe and Riverview).
As the area’s population grew, so did the needs of the community and, by extension, the number of officers and civilian staff.
Around 2010, discussions began on the topic of renovating/expanding the existing facility, or building a new one.
Chronology
The process was initiated in 2012, when a firm was hired to conduct a feasibility study. Since then, there have been many checkpoints and milestones with Moncton City Council – in fact, elected officials were consulted or informed of progress multiple times since 2013.
Some highlights, as well as next steps, are outlined in the timeline document found in the ‘Resources’ section to the right.
Current Building
There are numerous challenges with the current building, including:
- The building is currently at electrical capacity.
- The building does not meet post-disaster requirements.
- The building has suffered from multiple leaks and floods, leading to significant water infiltration throughout the building.
- The building lacks sufficient space and critical components of policing operations, such as the Operations Command Centre (OCC Dispatch), have been required to move off-site until a new building is constructed.
- It was built over 40 years ago for a single police force (before policing was a regional service for Moncton, Riverview, and Dieppe).
- The safety of both employees and individuals detained for arrest is at risk.
- Numerous building code deficiencies have been identified.
Project Cost
Clearly, a new policing facility isn’t a regular construction project. Beyond stringent security guidelines to follow, the work that will happen here is specialized, therefore has unique needs. Some examples include the construction materials that must be used in certain areas of the building, and the technical nature of some products. This type of specialty construction can be much different than typical commercial construction.
Budgeted components
$57.2M = total project cost estimate
- Land acquisition
- Site remediation and preparation
- Professional services (i.e. architectural/engineering firms, project management, testing and geotechnical services)
- Construction costs and appropriate contingencies
- Furniture and fixtures
- Information technology systems
- Security System components
- Legal Fees
- Public Art component
- HST costs
All companies hired to execute work were selected through public procurement processes. This will also be the case for the construction of the building itself.
Budget
On March 21, 2022, Moncton City Council awarded the tender for the construction of the Codiac regional policing facility. A total of five compliant tender submissions were received for this project and the lowest bid was awarded.
The total project cost, including the construction tender awarded, is $57,177,130 (less than the estimated value of $57,223,626 as updated in the fall of 2021). The full cost breakdown is as follows:
Budget Item | Cost |
Professional Services Fees | $5,324,283 |
Facility Construction | $40,839,575 |
Other Costs (furniture and fixtures, IT equipment, security equipment, soft costs, land purchase and remediation, contingency allowance) | $8,702,841 |
HST = 4.286% | $2,310,611 |
TOTAL PROJECT COST | $57,177,310 |
Construction update (January 2024)
- The project is 40 per cent complete and is currently on budget.
- Substantial completion is expected in March 2025 and the facility should be ready for occupancy in Summer 2025.
- Requests for pre-qualification of Indigenous artists for creation of public art for the facility, move management services, and property management services have all gone to tender.
As the project progresses, residents are encouraged to refer back here regularly for updates and milestones.
Background
The current station on Main Street was built in the 1970s when Moncton had a much smaller-scale police force.
Fast forward to the 1990s, when the local police force was converted to a tri-community force, offered by what is now known as the Codiac Regional RCMP (serving Moncton, Dieppe and Riverview).
As the area’s population grew, so did the needs of the community and, by extension, the number of officers and civilian staff.
Around 2010, discussions began on the topic of renovating/expanding the existing facility, or building a new one.
Chronology
The process was initiated in 2012, when a firm was hired to conduct a feasibility study. Since then, there have been many checkpoints and milestones with Moncton City Council – in fact, elected officials were consulted or informed of progress multiple times since 2013.
Some highlights, as well as next steps, are outlined in the timeline document found in the ‘Resources’ section to the right.
Current Building
There are numerous challenges with the current building, including:
- The building is currently at electrical capacity.
- The building does not meet post-disaster requirements.
- The building has suffered from multiple leaks and floods, leading to significant water infiltration throughout the building.
- The building lacks sufficient space and critical components of policing operations, such as the Operations Command Centre (OCC Dispatch), have been required to move off-site until a new building is constructed.
- It was built over 40 years ago for a single police force (before policing was a regional service for Moncton, Riverview, and Dieppe).
- The safety of both employees and individuals detained for arrest is at risk.
- Numerous building code deficiencies have been identified.
Project Cost
Clearly, a new policing facility isn’t a regular construction project. Beyond stringent security guidelines to follow, the work that will happen here is specialized, therefore has unique needs. Some examples include the construction materials that must be used in certain areas of the building, and the technical nature of some products. This type of specialty construction can be much different than typical commercial construction.
Budgeted components
$57.2M = total project cost estimate
- Land acquisition
- Site remediation and preparation
- Professional services (i.e. architectural/engineering firms, project management, testing and geotechnical services)
- Construction costs and appropriate contingencies
- Furniture and fixtures
- Information technology systems
- Security System components
- Legal Fees
- Public Art component
- HST costs
All companies hired to execute work were selected through public procurement processes. This will also be the case for the construction of the building itself.
Budget
On March 21, 2022, Moncton City Council awarded the tender for the construction of the Codiac regional policing facility. A total of five compliant tender submissions were received for this project and the lowest bid was awarded.
The total project cost, including the construction tender awarded, is $57,177,130 (less than the estimated value of $57,223,626 as updated in the fall of 2021). The full cost breakdown is as follows:
Budget Item | Cost |
Professional Services Fees | $5,324,283 |
Facility Construction | $40,839,575 |
Other Costs (furniture and fixtures, IT equipment, security equipment, soft costs, land purchase and remediation, contingency allowance) | $8,702,841 |
HST = 4.286% | $2,310,611 |
TOTAL PROJECT COST | $57,177,310 |
Construction update (January 2024)
- The project is 40 per cent complete and is currently on budget.
- Substantial completion is expected in March 2025 and the facility should be ready for occupancy in Summer 2025.
- Requests for pre-qualification of Indigenous artists for creation of public art for the facility, move management services, and property management services have all gone to tender.
As the project progresses, residents are encouraged to refer back here regularly for updates and milestones.
Questions?
Any question submitted will be reviewed by the project team, and depending on the nature of the question, a response will be provided either publicly in this section, or privately, within 2-3 business days.
Thank you for your interest!
-
Share I just want to thank Michelle for the response and information about the new RCMP building. . I really appreciate it on Facebook Share I just want to thank Michelle for the response and information about the new RCMP building. . I really appreciate it on Twitter Share I just want to thank Michelle for the response and information about the new RCMP building. . I really appreciate it on Linkedin Email I just want to thank Michelle for the response and information about the new RCMP building. . I really appreciate it link
I just want to thank Michelle for the response and information about the new RCMP building. . I really appreciate it
Jim Steeves asked about 2 years agoYou are very welcome. I'm glad to hear that you found the information helpful! :)
Thanks,
Michelle -
Share What were the other tender prices? on Facebook Share What were the other tender prices? on Twitter Share What were the other tender prices? on Linkedin Email What were the other tender prices? link
What were the other tender prices?
Meahan asked about 2 years agoHi there-
A total of five bids were received in response to this tender (including HST @ 15%):
- Pomerleau Inc.- $46,965,511.25 (successful bid)
- Marco Group Ltd.- $48,038,950.00
- Bird Construction Group- $50,341,250.00
- PCL Constructors Canada Inc.- $52,831,000.00
- Foulem Management Ltd.- $52,928,750.00
Thanks,
Austin
-
Share If the construction costs exceed the tendered bid, who is on the hook for that. Did pomerleau inc place a low bid knowing if they go over costs that the city will open the check book and give the extra funds with no penalties. Just out of curiosity, how many new city owned buildings came in at the tender bid or lower? on Facebook Share If the construction costs exceed the tendered bid, who is on the hook for that. Did pomerleau inc place a low bid knowing if they go over costs that the city will open the check book and give the extra funds with no penalties. Just out of curiosity, how many new city owned buildings came in at the tender bid or lower? on Twitter Share If the construction costs exceed the tendered bid, who is on the hook for that. Did pomerleau inc place a low bid knowing if they go over costs that the city will open the check book and give the extra funds with no penalties. Just out of curiosity, how many new city owned buildings came in at the tender bid or lower? on Linkedin Email If the construction costs exceed the tendered bid, who is on the hook for that. Did pomerleau inc place a low bid knowing if they go over costs that the city will open the check book and give the extra funds with no penalties. Just out of curiosity, how many new city owned buildings came in at the tender bid or lower? link
If the construction costs exceed the tendered bid, who is on the hook for that. Did pomerleau inc place a low bid knowing if they go over costs that the city will open the check book and give the extra funds with no penalties. Just out of curiosity, how many new city owned buildings came in at the tender bid or lower?
Matt asked about 2 years agoGood afternoon - thank you for your question.
When a Contractor submits a bid price in response to a Tender, they are entering into a contractual obligation to fully deliver the product or services detailed in the Tender documents for the bid price they (the Contractor) have indicated in their bid response, which is the price that is “awarded / agreed to” by the City of Moncton for the work. The Contractor is not entitled to any additional monies unless the Owner (in this case, the City of Moncton) makes a request that the Contractor deviate from the original specifications and drawings detailed in the Tender document, or there is an unknown / unforeseen condition which none of the parties were aware of at the time the bidding process took place which will require the Contractor to deviate from the original scope of work. However, the extra costs associated to address the unknown / unforeseen condition must be agreed upon and approved by the City prior to the change taking place.
Thanks,
Michelle -
Share Why do these buildings have to be so luxurious and expensive when officers should only be spending limited time there? How many RCMP will occupy this building? I think it's time to return to a municipal force, don't you? on Facebook Share Why do these buildings have to be so luxurious and expensive when officers should only be spending limited time there? How many RCMP will occupy this building? I think it's time to return to a municipal force, don't you? on Twitter Share Why do these buildings have to be so luxurious and expensive when officers should only be spending limited time there? How many RCMP will occupy this building? I think it's time to return to a municipal force, don't you? on Linkedin Email Why do these buildings have to be so luxurious and expensive when officers should only be spending limited time there? How many RCMP will occupy this building? I think it's time to return to a municipal force, don't you? link
Why do these buildings have to be so luxurious and expensive when officers should only be spending limited time there? How many RCMP will occupy this building? I think it's time to return to a municipal force, don't you?
Jim Steeves asked over 2 years agoGood afternoon - thank you for your questions on the regional policing facility.
The existing policing facility on Main Street does not address the operational needs of current regional police force (Codiac Regional RCMP). The building is used for much more than just officers and also needs to be designed with future growth in mind.
The new policing facility will have a total gross area of 6,683 sqm (71,935 sq.ft), excluding the mechanical penthouse. With 376 staff (estimate of total staff between municipal employees and RCMP members in 25 years), it represents approximately 17.8 sqm per person. As part of the planning process, a review of recently-built policing facilities was conducted. It revealed that a municipal police headquarters serving a community of similar size to that of the tri-community typically allocate between 22 and 28 sqm (250 to 300 sq.ft) per person. The design and features of the building were done to consider the functionalities of the police force and not just officers. You can see the percentages of space allocated for each type of space in the FAQ section on the right-hand side of this project page (under resources).
As it relates to a municipal police force, Moncton City Council will be conducting a study this year on the needs of policing in the tri-community and the best model to serve those needs. As part of the planning process for this facility, a report was completed to identify what could happen if there was a change in the current policing model. This report identifies that the facility could welcome an independent police service with a potential need of modifications to reflect the differing functions between the current RCMP model and an independent police service, so should a change happen, the building can be modified and expanded to meet those needs.
Thanks,
Michelle -
Share Will the city need a new building after 25 years or will it be able upgrade this new one? Is there a possibility that a municipal police force would replace the RCMP in the future? If so, how would it affect the use of the building? on Facebook Share Will the city need a new building after 25 years or will it be able upgrade this new one? Is there a possibility that a municipal police force would replace the RCMP in the future? If so, how would it affect the use of the building? on Twitter Share Will the city need a new building after 25 years or will it be able upgrade this new one? Is there a possibility that a municipal police force would replace the RCMP in the future? If so, how would it affect the use of the building? on Linkedin Email Will the city need a new building after 25 years or will it be able upgrade this new one? Is there a possibility that a municipal police force would replace the RCMP in the future? If so, how would it affect the use of the building? link
Will the city need a new building after 25 years or will it be able upgrade this new one? Is there a possibility that a municipal police force would replace the RCMP in the future? If so, how would it affect the use of the building?
Alfred asked about 2 years agoHi there, thank you for your question.
Designing for 25 year growth is considered standard practice for this type of facility (the life expectancy of the building is greater than 25 years). As part of the design stage, a “Comparison Report for Alternate Police Service Delivery Model” was completed when considering a new facility to identify what could happen if there was a change in the current policing model, through the RCMP. This report identifies that the facility could welcome an independent police service with a potential need of modifications to reflect the differing functions between the current RCMP model and an independent police service. It is predicted that the facility could not likely meet the long-term staff growth needs as designed, but the building could be expanded to the West as required.
Thanks,
Michelle -
Share Are we possibly considering going back to a municipal police force. on Facebook Share Are we possibly considering going back to a municipal police force. on Twitter Share Are we possibly considering going back to a municipal police force. on Linkedin Email Are we possibly considering going back to a municipal police force. link
Are we possibly considering going back to a municipal police force.
Mark McLellan asked over 2 years agoGood morning - thank you for your question. This possibility was studied by Moncton City Council in 2010, and it was determined at that time that a municipal police force was not in the best interest of the City. To be considered once again would require the will of City Council to undertake an extensive study on the topic.
-
Share I understand this is a regional building for Riverview, Dieppe and Moncton RCMP. Will the proceeds of the sale of the current 3 (or more) RCMP buildings be put toward paying down the cost of the new building? If yes, is there any estimate how much could be raised by the sale of current facilities? on Facebook Share I understand this is a regional building for Riverview, Dieppe and Moncton RCMP. Will the proceeds of the sale of the current 3 (or more) RCMP buildings be put toward paying down the cost of the new building? If yes, is there any estimate how much could be raised by the sale of current facilities? on Twitter Share I understand this is a regional building for Riverview, Dieppe and Moncton RCMP. Will the proceeds of the sale of the current 3 (or more) RCMP buildings be put toward paying down the cost of the new building? If yes, is there any estimate how much could be raised by the sale of current facilities? on Linkedin Email I understand this is a regional building for Riverview, Dieppe and Moncton RCMP. Will the proceeds of the sale of the current 3 (or more) RCMP buildings be put toward paying down the cost of the new building? If yes, is there any estimate how much could be raised by the sale of current facilities? link
I understand this is a regional building for Riverview, Dieppe and Moncton RCMP. Will the proceeds of the sale of the current 3 (or more) RCMP buildings be put toward paying down the cost of the new building? If yes, is there any estimate how much could be raised by the sale of current facilities?
DLS asked about 3 years agoHello,
At present, the regional force (Codiac RCMP) is operating out of one building in Moncton and the 911 call centre is located in Dieppe. Because of the age, condition and limited size of the Moncton building, the new building is being planned that will allow for future growth with most efficient operations. As well, with the additional space, the 911 call centre will be operated in the same new facility thus eliminating a separate facility and allowing for consolidated operations.
The Dieppe building is owned by Dieppe and they will determine the future use or sale of that facility. The current RCMP regional building located in Moncton (as noted above) is owned by the City of Moncton. Any proceeds from the sale/repurposing of that building will become revenues to the City of Moncton. Administration will propose options to Council as to the use of these proceeds when the future sale/repurposing transpires.
Kind regards,
Nicole -
Share If you publish the intail cost of $46 million why wont you tell us the price now before the election on Facebook Share If you publish the intail cost of $46 million why wont you tell us the price now before the election on Twitter Share If you publish the intail cost of $46 million why wont you tell us the price now before the election on Linkedin Email If you publish the intail cost of $46 million why wont you tell us the price now before the election link
If you publish the intail cost of $46 million why wont you tell us the price now before the election
Wink asked about 3 years agoHello,
The estimate is under review and has therefore not been finalized. City Administration will be working with the design team in the next few months to complete a detailed review.
Once this has been completed, if the net estimated amount differs from what was approved by City Council during capital budget deliberations in November 2020, City Council will have to approve the revised net project cost (and borrowing amount).
Kind regards,
Nicole -
Share $46 million??? and that's before the overruns which will significantly enlarge this figure. In these times of covid and recession, is this a spending and community priority? There is ample commercial space available and to become available to meet policing needs and programs and outreach services that are desperately needed in Moncton. Better to address the poverty and homeless social issues in this city than literally waste such monies that will assuredly not improve current policing services. (I know...social programs are a Provincial issue. I beg to differ. They are a community's issue.) A better question for Council to ask itself is: Does the local infrastructure support current policing needs? The answer would be yes, as I haven't read or heard otherwise, even from RCMP sources. The next question: So, how do we meet the infrastructure needs of the future? Answer: Find out what they are, specifically and based on empirical data and assumptions, and cost-effectively brain-storm the solutions. There now; just saved you $46 plus million. on Facebook Share $46 million??? and that's before the overruns which will significantly enlarge this figure. In these times of covid and recession, is this a spending and community priority? There is ample commercial space available and to become available to meet policing needs and programs and outreach services that are desperately needed in Moncton. Better to address the poverty and homeless social issues in this city than literally waste such monies that will assuredly not improve current policing services. (I know...social programs are a Provincial issue. I beg to differ. They are a community's issue.) A better question for Council to ask itself is: Does the local infrastructure support current policing needs? The answer would be yes, as I haven't read or heard otherwise, even from RCMP sources. The next question: So, how do we meet the infrastructure needs of the future? Answer: Find out what they are, specifically and based on empirical data and assumptions, and cost-effectively brain-storm the solutions. There now; just saved you $46 plus million. on Twitter Share $46 million??? and that's before the overruns which will significantly enlarge this figure. In these times of covid and recession, is this a spending and community priority? There is ample commercial space available and to become available to meet policing needs and programs and outreach services that are desperately needed in Moncton. Better to address the poverty and homeless social issues in this city than literally waste such monies that will assuredly not improve current policing services. (I know...social programs are a Provincial issue. I beg to differ. They are a community's issue.) A better question for Council to ask itself is: Does the local infrastructure support current policing needs? The answer would be yes, as I haven't read or heard otherwise, even from RCMP sources. The next question: So, how do we meet the infrastructure needs of the future? Answer: Find out what they are, specifically and based on empirical data and assumptions, and cost-effectively brain-storm the solutions. There now; just saved you $46 plus million. on Linkedin Email $46 million??? and that's before the overruns which will significantly enlarge this figure. In these times of covid and recession, is this a spending and community priority? There is ample commercial space available and to become available to meet policing needs and programs and outreach services that are desperately needed in Moncton. Better to address the poverty and homeless social issues in this city than literally waste such monies that will assuredly not improve current policing services. (I know...social programs are a Provincial issue. I beg to differ. They are a community's issue.) A better question for Council to ask itself is: Does the local infrastructure support current policing needs? The answer would be yes, as I haven't read or heard otherwise, even from RCMP sources. The next question: So, how do we meet the infrastructure needs of the future? Answer: Find out what they are, specifically and based on empirical data and assumptions, and cost-effectively brain-storm the solutions. There now; just saved you $46 plus million. link
$46 million??? and that's before the overruns which will significantly enlarge this figure. In these times of covid and recession, is this a spending and community priority? There is ample commercial space available and to become available to meet policing needs and programs and outreach services that are desperately needed in Moncton. Better to address the poverty and homeless social issues in this city than literally waste such monies that will assuredly not improve current policing services. (I know...social programs are a Provincial issue. I beg to differ. They are a community's issue.) A better question for Council to ask itself is: Does the local infrastructure support current policing needs? The answer would be yes, as I haven't read or heard otherwise, even from RCMP sources. The next question: So, how do we meet the infrastructure needs of the future? Answer: Find out what they are, specifically and based on empirical data and assumptions, and cost-effectively brain-storm the solutions. There now; just saved you $46 plus million.
DHA asked over 3 years agoThank you for sharing your thoughts on the project.
-
Share In 2013, the City of Saint John built an 110,000 sq. ft. Police and Law Court facility for just over $22 Million (adjusted for inflation, it’s $24,426,601.78) In comparison, the Codiac RCMP Facility is planned to be 69, 567 sq. ft. in size, and coming in at a cost of ~$45 Million. (40, 433 sq. ft. smaller than Saint John, and and costing twice as much.) The costs don't make sense! on Facebook Share In 2013, the City of Saint John built an 110,000 sq. ft. Police and Law Court facility for just over $22 Million (adjusted for inflation, it’s $24,426,601.78) In comparison, the Codiac RCMP Facility is planned to be 69, 567 sq. ft. in size, and coming in at a cost of ~$45 Million. (40, 433 sq. ft. smaller than Saint John, and and costing twice as much.) The costs don't make sense! on Twitter Share In 2013, the City of Saint John built an 110,000 sq. ft. Police and Law Court facility for just over $22 Million (adjusted for inflation, it’s $24,426,601.78) In comparison, the Codiac RCMP Facility is planned to be 69, 567 sq. ft. in size, and coming in at a cost of ~$45 Million. (40, 433 sq. ft. smaller than Saint John, and and costing twice as much.) The costs don't make sense! on Linkedin Email In 2013, the City of Saint John built an 110,000 sq. ft. Police and Law Court facility for just over $22 Million (adjusted for inflation, it’s $24,426,601.78) In comparison, the Codiac RCMP Facility is planned to be 69, 567 sq. ft. in size, and coming in at a cost of ~$45 Million. (40, 433 sq. ft. smaller than Saint John, and and costing twice as much.) The costs don't make sense! link
In 2013, the City of Saint John built an 110,000 sq. ft. Police and Law Court facility for just over $22 Million (adjusted for inflation, it’s $24,426,601.78) In comparison, the Codiac RCMP Facility is planned to be 69, 567 sq. ft. in size, and coming in at a cost of ~$45 Million. (40, 433 sq. ft. smaller than Saint John, and and costing twice as much.) The costs don't make sense!
Hafsah asked over 3 years agoThank you for your question.
Square footage refers mainly to construction costs, whereas the figure of $45 million referred to for the Moncton facility includes many other elements, such as land purchase, site (environmental) remediation, furnishings, etc.
The City of Moncton continues to work with subject-matter experts to further refine estimates for these various components at each step of the process, taking into account current realities.
FAQs
-
Why is a new facility required?
- Why isn’t the existing facility being renovated/expended instead of building a new facility on a new site?
- Why is a new facility required?
- What has the City done to analyze the need for a new building?
- Where can I find out more about the updates on the regional policing facility?
- Why is some information in this project confidential?
-
The Proposed Building
- Do other cities have buildings this size for their policing facilities?
- Why is the facility designed for 25 years?
- Would it be more feasible/cost effective to have a three- or four-story building?
- What will be in the new facility, and how will the space be allocated?
- What is the anticipated project schedule?
- How will the new facility contain environmentally-friendly elements?
-
Policing Model and Future of Policing
- What methodology was used to estimate the number of employees in 25 years?
- When did the RCMP assume responsibility for policing?
- What if the tri-community was to move forward with a regional police force in the future, could the building be adapted?
- What is the current number of staff and the future projections?
- What is the role of the Codiac Regional Policing Authority (CRPA) in the new building?
- Project Cost Estimates